|
|
Project Schedule
—
filed under:
Projects
This is a tentative schedule: Phase 1 - Remove the median on 104th Avenue to Bannock Street and patched it. This phase was completed in July. Phase 2 - Mid-July through mid-November: The northern portion of the bridge will be demolished and rebuilt. This phase is underway. Phase 3 - Mid-November through mid-March 2010: The center portion of the bridge will be demolished and rebuilt. Phase 4 - Mid-March 2010 through to mid-September 2010: The southern portion of the bridge will be demolished and rebuilt. This will complete the project.
Document Actions |
Contact Information
Mindy Crane |
