Project Schedule
—
filed under:
Projects
This is a tentative schedule: Phase 1- Remove the median on 104th Avenue to Bannock Street and patched it. This phase was completed in July. Phase 2- Mid-July through mid-November: The northern portion of the bridge will be demolished and rebuilt. This phase is underway. Phase 3- Mid-November through mid-March 2010: The center portion of the bridge will be demolished and rebuilt. Phase 4- Mid-March 2010 through to mid-September 2010: The southern portion of the bridge will be demolished and rebuilt. This will complete the project.