I-70 Viaduct Expansion Joint Repairs
—
filed under:
Denver Metro Area (Region 6),
Projects
In September 2008, the Colorado Department of Transportation (CDOT) began an
The project is estimated to take over two years to complete and the estimated completion date is the spring of 2011. American Civil Constructors, Inc. is the contractor for this project. Construction UpdateSince the project began, crews have replaced 74 bridge drains, constructed shoring towers, which are necessary to begin the expansion joint work, and conducted some minor roadways repairs. In late January, the crews started the expansion joint work.
Lane Closures
The expansion joint work requires single lane closures on eastbound and westbound I-70 starting at 8 p.m. with a second lane closing at 10 p.m. All lanes will reopen by 5:30 a.m. the following day. Lane closures can be expected Sunday through Saturday, but currently crews are only working Sunday through Thursday.