Bridge Construction Updates

US 36 BRIDGE OVER LOWELL BOULEVARD SCHEDULE

  • December 2012 – Bridge girders installed
  • January 2013 – Bridge deck pour
  • February 2013 – Work on approach slabs and roadway construction
  • March 2013 – Demolition of existing bridge through the median after initial traffic realignment
  • April-July 2013 – Construct new bridge through median

 

SHERIDAN BRIDGE SCHEDULE

  • January-March 2013 – Phase one foundation and substructure
  • April-June 2013 – Phase one bridge and roadway construction
  • July 2013 – Realign traffic to new bridge/begin phase two bridge construction
  • July 2013 – Demolition of phase one of the existing Sheridan bridge
  • Sheridan Bridge Exhibit

 

BNSF BRIDGE SCHEDULE

  • December 2012-January 2013 – Westbound wing walls under construction  (currently 90 percent complete)
  • February 2013 – Demolish phase one of the existing BNSF bridge
  • February-July 2013 – Phase one bridge construction

 

US 36 BRIDGE OVER PROMENADE SCHEDULE

  • April 2013 – Phase one of bridge demolition
  • May 2013 – Phase one bridge substructure work begins
  • June 2013 – Girder and bridge deck installation

 

WADSWORTH PARKWAY AND 112th AVENUE BRIDGE SCHEDULES

  • December 2012-February 2013
    • Bridge foundation work
    • Construct Mechanically Stabilized Earth (MSE) walls
    • Construct bridge abutments
    • Construct caissons, columns and pier caps
  • February 2013-March 2013
    • Bridge structure work
    • Place bridge girders
    • Pour the concrete bridge deck
  • March 2013-May 2013
    • Bridge support construction
    • Construct bridge approaches
    • Construct bridge tie-ins
    • Construct new roadways and bridge ramps
  • June 2013-November 2013
    • Move traffic onto the new bridge
    • Demolish the existing bridge structure
    • Construct roadway to the north and south of the new bridge structure
    • Finish bridge tie-ins
    • Wadsworth Parkway Bridge Exhibit