Tentative Project Schedule

This is a tentative schedule of construction activities.

Winter/spring 2013

  • Traffic realignments of both the east and westbound lanes
  • Crews will be working in the median to install drainage culverts
  • Bridge work will continue on the US 36 bridge over Lowell Boulevard with traffic being realigned to new bridge in spring 2013
  • Sheridan Boulevard bridge being constructed alongside existing bridge

 

Spring/summer 2013

  • Construction of the new US 36 bridge over Lowell Boulevard will continue through late summer
  • Permanent pavement being laid on eastbound lanes

 

Fall/winter 2013

  • US 36 bridge over Lowell Boulevard completed
  • 112th Avenue and Wadsworth Parkway bridges completed
  • Permanent pavement being laid on eastbound lanes