CDOT Owned ARRA Project Map
-
Union Pacific Railroad Roundhouse
-
| Project Owner |
Lincoln County |
| CDOT Region |
1 |
| County |
Lincoln |
| Description of Work |
Restores the only surviving brick roundhouse in the state and the last one affiliated with the Union Pacific Railroad. Project includes rebuilding the tar and pitch roof. When complete, the roundhouse will become a railroad museum. |
| Estimated Total Project Cost |
$756,900 |
| ARRA Funds |
$555,000 |
| Project Status |
Under Construction |
| Start Date |
Janaury 25, 2010 |
| Completion Date |
December 2010 |
| Percentage Spent |
N/A |
| Contractor |
TBD |
-
39.7364982875
-103.367271423
-
- Central/Eastern Colorado (Region 1)
- ARRA
- ARRA-Enhancement
- Lincoln County
- Project: UPR Roundhouse
- Projects
-
US 34 between Brush and Akron
-
| Project Owner |
CDOT |
| CDOT Region |
4 |
| County |
Morgan/Washington |
| Description of Work |
Chip seals 15 miles of US 34 to improve the roadway surface condition. |
| Estimated Total Project Cost |
$2,300,000 |
| ARRA Funds |
$1,669,000 |
| Project Status |
Completed |
| Start Date |
June 13, 2011 |
| Completion Date |
|
| Percentage Spent |
N/A |
| Contractor |
Intermountain Slurry Seal, Inc. |
-
40.2163733107
-103.362464905
-
- Morgan County
- ARRA
- ARRA-CDOT
- Project: US 34 Akron to Brush
- Washington County
- Northeastern (Region 4)
- Projects
-
Big Timbers Transportation Museum
-
| Project Owner |
Prowers County |
| CDOT Region |
2 |
| County |
Prowers County |
| Description of Work |
Designs and constructs a transportation museum. |
| Estimated Total Project Cost |
$646,140 |
| ARRA Funds |
$330,750 |
| Project Status |
Completed
|
| Start Date |
|
| Completion Date |
|
| Percentage Spent |
N/A |
| Contractor |
|
-
38.0172630254
-106.066818237
-
- ARRA
- ARRA-Enhancement
- Project: Big Timbers Museum
- Prowers County
- Southeastern Colorado (Region 2)
- Projects
-
US 24 west of Limon
-
| Project Owner |
CDOT |
| CDOT Region |
1 |
| County |
Elbert |
| Description of Work |
Resurfaces 10.8 miles of US 24 in asphalt. |
| Estimated Total Project Cost |
$6,851,078 |
| ARRA Funds |
$6,717,078 |
| Project Status |
Completed
|
| Start Date |
May 2010 |
| Completion Date |
August 2010 |
| Percentage Spent |
N/A |
| Contractor |
APC Southern Construction Co. |
-
39.2583098225
-103.728103638
-
- ARRA
- ARRA-CDOT
- Elbert County
- Project: US 24 west of Limon
- Projects
-
Clear Creek County Bakerville to Loveland Recreational Trail
-
| Project Owner |
Clear Creek County |
| CDOT Region |
1 |
| County |
Clear Creek County |
| Description of Work |
Paves 2.88 miles of the existing 4.88 miles trail in asphalt. Another phase will be required to complete the paving of the remaining two miles. |
| Estimated Total Project Cost |
$513,635 |
| ARRA Funds |
$513,635 |
| Project Status |
Under Ad as of January 6, 2010 |
| Start Date |
TBD |
| Completion Date |
TBD |
| Percentage Spent |
N/A |
| Contractor |
TBD |
-
39.7507534945
-105.550804138
-
- Central/Eastern Colorado (Region 1)
- ARRA
- ARRA-Enhancement
- Clear Creek County
- Project: CCC Recreational Trail
- Projects
-
Bent County Courthouse
-
| Project Owner |
Bent County |
| CDOT Region |
2 |
| County |
Bent County |
| Description of Work |
Historic restoration through Town Square including streetscaping, sidewalks and landscaping. |
| Estimated Total Project Cost |
$420,106 |
| ARRA Funds |
$121,000 |
| Project Status |
|
| Start Date |
|
| Completion Date |
|
| Percentage Spent |
N/A |
| Contractor |
|
-
38.0172630254
-106.066818237
-
- Central/Eastern Colorado (Region 1)
- ARRA
- Project: Bent County Courthouse
- ARRA-Enhancement
- Bent County
- Projects
-
Northern Avenue Trail Enhancement
-
| Project Owner |
City of Pueblo |
| CDOT Region |
2 |
| County |
Pueblo County |
| Description of Work |
Pedestrian trail replacement and streetscape on Northern Avenue from Vinewood Lane to Prairie Avenue. |
| Estimated Total Project Cost |
$506,013 |
| ARRA Funds |
$165,000 |
| Project Status |
|
| Start Date |
|
| Completion Date |
|
| Percentage Spent |
N/A |
| Contractor |
|
-
38.2363509
-104.6611019
-
- Pueblo County
- ARRA
- ARRA-Enhancement
- Southeastern Colorado (Region 2)
- Project: Northern Avenue Trail
- Projects
-
C-470/US 85 (Santa Fe Drive) Interchange
-
| CDOT Region |
6 |
| County |
Douglas |
| Description of Work |
Constructs a flyover ramp from southbound Santa Fe Drive to eastbound C-470 to improve safety and mobility. |
| Estimated Total Project Cost |
$25,691,489 |
| ARRA Funds |
$4,582,634 |
| Project Status |
Under Ad as of January 28, 2010 |
| Start Date |
TBD |
| Completion Date |
TBD |
| Percentage Spent |
N/A |
| Contractor |
TBD |
-
39.5644118563
-105.033416748
-
- ARRA
- ARRA-CDOT
- Project: C-470 at Santa Fe Dr.
- Douglas County
- Denver Metro Area (Region 6)
- Projects
-
I-70 West, Truck Parking Management
-
| Project Owner |
CDOT |
| CDOT Region |
1 |
| County |
Clear Creek and Eagle |
| Description of Work |
Installs various truck parking management components (electronic signs, closed-circuit cameras, power and communications systems), as identified in the I-70 Mountain Corridor PEIS, to provide notification during inclement weather. |
| Estimated Total Project Cost |
$2,048,253 |
| ARRA Funds |
$2,014,973 |
| Project Status |
Completed
|
| Start Date |
August 10, 2009 |
| Completion Date |
March 2010 |
| Percentage Spent |
N/A |
| Contractor |
Sturgeon Electric Co.
|
-
39.6460146605
-107.072753906
-
- Project: I-70 Truck Parking Mgmt.
- ARRA
- ARRA-CDOT
- Eagle County
- Clear Creek County
- Projects
-
State Highway 2 between 62nd Avenue and Quebec Parkway
-
| Project Owner |
CDOT |
| CDOT Region |
6 |
| County |
Denver |
| Description of Work |
Resurfaces approximately 2.4 miles of SH 2 in asphalt. |
| Estimated Total Project Cost |
$3,154,125 |
| ARRA Funds |
$2,399,348 |
| Project Status |
Estimated Ad Date: February 2010 |
| Start Date |
TBD |
| Completion Date |
TBD |
| Percentage Spent |
N/A |
| Contractor |
TBD |
-
39.8284452612
-104.914112091
-
- ARRA
- ARRA-CDOT
- Denver County
- Project: SH 2 62nd to Quebec
- Projects
- Denver Metro Area (Region 6)
-
State Highway 14, Muddy Pass
-
| Project Owner |
CDOT |
| CDOT Region |
3 |
| County |
Jackson |
| Description of Work |
Resurfaces approximately 17 miles of SH 14 and improves shoulders and culverts. |
| Estimated Total Project Cost |
$8,970,808 |
| ARRA Funds |
$6,337,976 |
| Project Status |
Completed
|
| Start Date |
June 22, 2011 |
| Completion Date |
September 16, 2011
|
| Percentage Spent |
100% |
| Contractor |
A & S Construction |
-
40.3813360447
-106.578369141
-
- ARRA
- ARRA-CDOT
- Northwestern (Region 3)
- Project: I-70B near Grand Junction
- Projects
-
Platte River Pedestrian Bridge and Bicycle Path
-
| Project Owner |
CDOT |
| CDOT Region |
1 |
| County |
Park County |
| Description of Work |
Constructs a pedestrain bridge over the Platte River in Fairplay and resurfaces seven miles of the Platte River pedestrian/bicycle path. |
| Estimated Total Project Cost |
$436,000 |
| ARRA Funds |
$236,000 |
| Project Status |
Completed |
| Start Date |
|
| Completion Date |
|
| Percentage Spent |
N/A |
| Contractor |
NCB, LLC |
-
39.2189551877
-105.994720459
-
- Central/Eastern Colorado (Region 1)
- ARRA
- ARRA-Enhancement
- Park County
- Project: Platte River Ped/Bike Path
- Projects
-
John Rawlings Heritage Center
-
| Project Owner |
Bent County |
| CDOT Region |
2 |
| County |
City of Las Animas |
| Description of Work |
Historic restoration by construction sidewalks, landscaping, signage and parking lot rehabilitation |
| Estimated Total Project Cost |
$335,250 |
| ARRA Funds |
$68,453 |
| Project Status |
|
| Start Date |
|
| Completion Date |
|
| Percentage Spent |
N/A |
| Contractor |
|
-
38.0172630254
-106.066818237
-
- ARRA
- ARRA-Enhancement
- Bent County
- Project: John Rawlings Center
- Southeastern Colorado (Region 2)
- Projects
-
Pueblo Eastern Gateway Landscape
-
| Project Owner |
City of Pueblo |
| CDOT Region |
2 |
| County |
Pueblo County |
| Description of Work |
Landscaping and irrigation installation for the Eastern Gateway Landscape project located at the intersection of US 50B and SH 47. |
| Estimated Total Project Cost |
$437,424 |
| ARRA Funds |
$381,424 |
| Project Status |
|
| Start Date |
|
| Completion Date |
|
| Percentage Spent |
N/A |
| Contractor |
|
-
38.2748447678
-104.558944702
-
- Pueblo County
- ARRA
- ARRA-Enhancement
- Project: Pueblo Eastern Gateway
- Southeastern Colorado (Region 2)
- Projects
-
I-70 between Kipling Street and Wadsworth Boulevard
-
| Project Owner |
CDOT |
| CDOT Region |
6 |
| County |
Jefferson |
| Description of Work |
Repairs or replaces concrete slabs for approximately three miles of I-70. |
| Estimated Total Project Cost |
$2,313,025 |
| ARRA Funds |
$1,793,405 |
| Project Status |
Construction Complete |
| Start Date |
May 19, 2009 |
| Completion Date |
September 2009 |
| Percentage Spent |
100% |
| Contractor |
New Design Construction Co. |
-
39.7831467198
-105.09755516
-
- ARRA-CDOT
- Project: I-70 Kipling to Wadsworth
- Jefferson County
- Denver Metro Area (Region 6)
- ARRA
- Projects
-
Overview
-
| Project Owner |
CDOT |
| CDOT Region |
1 |
| County |
Summit |
| Description of Work |
Widens SH 9 to two lanes in each direction and constructs a new pedestrian bridge and a retaining wall. The project will also relocate a bike path and improve drainage. |
| Estimated Total Project Cost |
$9,250,128 |
| ARRA Funds |
$8,994,331 |
| Project Status |
Completed
|
| Start Date |
June 15, 2009 |
| Completion Date |
August 2010 |
| Percentage Spent |
100% |
| Contractor |
Zak Dirt, Inc.
|
-
39.5069214429
-106.047978401
-
- Project: SH 9 Valley Brook to Coyne Valley
- Central/Eastern Colorado (Region 1)
- ARRA
- ARRA-CDOT
- Summit County
- Projects
-
Overview
-
| Description of Work |
Widens one mile of US 85 to two lanes in each directions with shoulders and a raised median with controlled access. The existing roadway is only one lane in each direction with no shoulders. |
| Project Owner |
CDOT |
| CDOT Region |
1 |
| County |
Douglas |
| Estimated Total Project Cost |
$6,701,038 |
| ARRA Funds |
$5,400,000 |
| Project Status |
Completed
|
| Start Date |
September 21, 2009 |
| Completion Date |
July 2010 |
| Percentage Spent |
100% |
| Contractor |
Lawson Construction, Co. |
-
39.5117224064
-105.020027161
-
- ARRA
- ARRA-CDOT
- Douglas County
- Project: US 85 Titan Road to Cook Ranch
- Projects
-
C-470 between I-25 and Santa Fe Drive
-
| CDOT Region |
6 |
| County |
Douglas |
| Description of Work |
Repairs or replaces concrete slabs on C-470 and resurfaces C-470 in asphalt. Rehabilitates the C-470 bike path between I-70 and I-25. |
| Estimated Total Project Cost |
$31,985,485 |
| ARRA Funds |
$31,465,789 |
| Project Status |
Under Construction |
| Start Date |
June 30, 2009 |
| Completion Date |
September 2010 |
| Percentage Spent |
30.13% |
| Contractor |
Castle Rock Construction Co. |
-
39.56361784
-104.92149353
-
- ARRA
- ARRA-CDOT
- Douglas County
- Denver Metro Area (Region 6)
- Project: C-470 I-25 to Santa Fe Dr.
- Projects
-
I-25 Through Trinidad
-
| Project Owner |
CDOT |
| CDOT Region |
2 |
| County |
Las Animas |
| Description of Work |
Constructs the Purgatoire River Pedestrian Trail, adds street lights, parking lot paving, curb and gutter, drainage inlets, landscaping and sidewalk. This work will be added onto the existing contract for work taking place on I-25 through Trinidad. |
| Estimated Total Project Cost |
$82.3 million |
| ARRA Funds |
$7,044,806 |
| Project Status |
Under Construction |
| Start Date |
December 2006 |
| Completion Date |
July 2011
|
| Percentage Spent |
|
| Contractor |
Lawrence Construction Co. |
| Web site |
http://www.i25trinidad.com/ |
-
37.1742693966
-104.50753212
-
- ARRA
- ARRA-CDOT
- Project: I-25 in Trinidad
- Southeastern Colorado (Region 2)
- Projects
-
Overview
-
| Description of Work |
Resurfaces 14 miles of I-70 from milepost 190 to 204 as well as the right lane of eastbound I-70 between milepost 180 and 190. Numerous bridges along the I-70 corridor will also be rehabilitated by repairing expansion joints and bridge decks. |
| Project Owner |
CDOT |
| CDOT Region |
1 |
| County |
Eagle and Summit |
| Estimated Total Project Cost |
$10,068,510 |
| ARRA Funds |
$8,000,000 |
| Project Status |
Completed |
| Start Date |
June 1, 2009 |
| Completion Date |
Summer 2010 |
| Percentage Spent |
N/A |
| Contractor |
Asphalt Paving Co. |
-
39.5520374016
-106.135568619
-
- Project: SH 9 Valley Brook to Coyne Valley
- ARRA
- ARRA-CDOT
- Eagle County
- Summit County
- Projects
-
I-25 between 6th Avenue and 23rd Avenue
-
| Project Owner |
CDOT |
| CDOT Region |
6 |
| County |
Denver |
| Description of Work |
Resurfaces approximately three miles of I-25 in asphalt. |
| Estimated Total Project Cost |
$4,259,920 |
| ARRA Funds |
$4,190,706 |
| Project Status |
Under Construction- In winter shutdown |
| Start Date |
June 14, 2009 |
| Completion Date |
April 2010 |
| Percentage Spent |
76% |
| Contractor |
Brannan Sand and Gravel Co. |
-
39.7389898615
-105.01404047
-
- Project: I-25 6th to 23rd
- ARRA-CDOT
- Denver County
- Denver Metro Area (Region 6)
- ARRA
- Projects
-
I-25, US 36 and C-470
-
| Project Owner |
CDOT |
| CDOT Region |
6 |
| County |
Adams, Douglas and Jefferson |
| Description of Work |
Installs ramp metering on the ramps from Sheridan Blvd. to westbound US 36, 84th Ave. to northbound I-25, Kipling Parkway to eastbound C-470 and Yosemite St. to westbound C-470. |
| Estimated Total Project Cost |
$338,997 |
| ARRA Funds |
$333,489 |
| Project Status |
Construction Complete |
| Start Date |
June 1, 2009 |
| Completion Date |
October 2009 |
| Percentage Spent |
100% |
| Contractor |
Colorado Boring Co. |
-
39.8619548715
-105.055818558
-
- ARRA
- ARRA-CDOT
- Jefferson County
- Douglas County
- Denver Metro Area (Region 6)
- Adams County
- Project: I-25/US 36/C-470
- Projects
-
I-25 at Alameda Avenue/Santa Fe Drive
-
| Project Owner |
CDOT |
| CDOT Region |
6 |
| County |
Denver |
| Description of Work |
Replaces the Alameda bridge over I-25 with one that is wider to accommodate an additional lane in each direction. |
| Estimated Total Project Cost |
$37,400,000 |
| ARRA Funds |
$35,447,157 |
| Project Status |
Under Construction |
| Start Date |
April 1, 2010 |
| Completion Date |
September 30, 2012
|
| Percentage Spent |
N/A |
| Contractor |
Jalisco International, Inc. |
| Website |
www.coloradodot.info/projects/I25Alameda |
-
39.7113134844
-104.999084473
-
- Project: I-25 at Alameda
- ARRA
- ARRA-CDOT
- Denver County
- Denver Metro Area (Region 6)
- Projects
-
I-25 between US 34 and State Highway 392
-
| Project Owner |
CDOT |
| CDOT Region |
4 |
| County |
Larimer |
| Description of Work |
Improves five miles of roadway surface on I-25. |
| Estimated Total Project Cost |
$7,000,000 |
| ARRA Funds |
$6,859,424 |
| Project Status |
Completed
|
| Start Date |
July 6, 2009 |
| Completion Date |
May 2010 |
| Percentage Spent |
N/A |
| Contractor |
Aggregate Industries |
-
40.4709796948
-104.992218018
-
- ARRA
- ARRA-CDOT
- Project: I-25 US 34 to SH 392
- Northeastern (Region 4)
- Projects
-
I-70/State Highway 82/US 6 at the Glenwood Springs Interchange (#116)
-
| Project Owner |
CDOT |
| CDOT Region |
3 |
| County |
Garfield |
| Description of Work |
This safety improvement project will upgrade traffic signals and improve ramp width and length to benefit both pedestrians and vehicles. |
| Estimated Total Project Cost |
$2,755,402 |
| ARRA Funds |
$2,500,000 |
| Project Status |
Construction Complete |
| Start Date |
August 17, 2009 |
| Completion Date |
November 2009 |
| Percentage Spent |
100% |
| Contractor |
Scott Contracting, Inc.
|
-
39.1176752384
-108.359355927
-
- ARRA
- ARRA-CDOT
- Project: I-70/SH82/US 6 at Glenwood Springs
- Northwestern (Region 3)
- Projects
-
I-70 at Palisade Interchange (#42)
-
| Project Owner |
CDOT |
| CDOT Region |
3 |
| County |
Mesa |
| Description of Work |
Improves safety by widening the acceleration and deceleration lanes at this interchange. The improvements will upgrade the interchange to current design standards. |
| Estimated Total Project Cost |
$1,361,584 |
| ARRA Funds |
$1,339,461 |
| Project Status |
Construction Complete |
| Start Date |
September 14, 2009 |
| Completion Date |
December 2009 |
| Percentage Spent |
100% |
| Contractor |
United Companies |
-
39.1176752384
-108.359355927
-
- ARRA
- ARRA-CDOT
- Northwestern (Region 3)
- Projects
- Project: I-70 Palisade
-
I-70 between Pena Boulevard and Tower Road
-
| Project Owner |
CDOT |
| CDOT Region |
6 |
| County |
Adams |
| Description of Work |
Installs median cable guardrail to prevent crossover accidents. |
| Estimated Total Project Cost |
$334,060 |
| ARRA Funds |
$328,632 |
| Project Status |
Construction Complete |
| Start Date |
July 20, 2009 |
| Completion Date |
August 2009 |
| Percentage Spent |
100.00% |
| Contractor |
Ideal Fencing Corp. |
-
39.7656655076
-104.790773392
-
- ARRA
- ARRA-CDOT
- Denver Metro Area (Region 6)
- Adams County
- Project: I-70 Pena Blvd. to Tower Rd.
- Projects
-
I-76 at 96th Avenue
-
| Project Owner |
CDOT |
| CDOT Region |
6 |
| County |
Adams |
| Description of Work |
Constructs roundabouts at this interchange. |
| Estimated Total Project Cost |
$4,004,163 |
| ARRA Funds |
$2,222,733 |
| Project Status |
Under Construction- In winter shutdown |
| Start Date |
June 22, 2009 |
| Completion Date |
May 2010 |
| Percentage Spent |
75% |
| Contractor |
Castle Rock Construction Co. |
-
39.870486171
-104.901752472
-
- Project: I-76 at 96th
- ARRA-CDOT
- Denver Metro Area (Region 6)
- ARRA
- Adams County
- Projects
-
I-76 over UPRR and State Highway 224
-
| Project Owner |
CDOT |
| CDOT Region |
6 |
| County |
Adams |
| Description of Work |
Replaces two bridges on I-76. |
| Estimated Total Project Cost |
$11,056,153 |
| ARRA Funds |
$10,876,514 |
| Project Status |
Under Construction |
| Start Date |
July 6, 2009 |
| Completion Date |
July 2010 |
| Percentage Spent |
40% |
| Contractor |
SEMA Construction, Inc. |
-
39.8289561007
-104.943981171
-
- ARRA
- ARRA-CDOT
- Project: I-76 over SH 224
- Denver Metro Area (Region 6)
- Adams County
- Projects
-
I-70 at the Edwards Interchange (#163)
-
| Project Owner |
CDOT |
| CDOT Region |
3 |
| County |
Eagle |
| Description of Work |
This safety improvement project will construct three roundabouts at the interchange. |
| Estimated Total Project Cost |
$11,000,000 |
| ARRA Funds |
$10,821,276 |
| Project Status |
Under Contract |
| Start Date |
TBD |
| Completion Date |
TBD |
| Percentage Spent |
N/A |
| Contractor |
American Civil Constructors, Inc. |
| Website |
http://www.coloradodot.info/projects/i70edwardsinterchange |
-
39.6496164565
-106.588797569
-
- Project: I-70 at Edwards
- ARRA
- ARRA-CDOT
- Northwestern (Region 3)
- Projects
-
SH 88 Between Belleview & Federal
-
| Project Owner |
CDOT |
| CDOT Region |
6 |
| County |
Arapahoe |
| Description of Work |
Resurfaces approximately one mile of SH 88 in asphalt. |
| Estimated Total Project Cost |
$676,523 |
| ARRA Funds |
$665,530 |
| Project Status |
Construction Complete |
| Start Date |
May 19, 2009 |
| Completion Date |
June 2009 |
| Percentage Spent |
100.00% |
| Contractor |
Aggregate Industries |
-
39.6242016127
-105.019426346
-
- ARRA
- ARRA-CDOT
- Arapahoe County
- Project: SH 88 Federal to US 85
- Denver Metro Area (Region 6)
-
Overview
-
| Project Owner |
CDOT |
| CDOT Region |
3 |
| County |
Rio Blanco |
| Description of Work |
Reconstructs five miles of SH 13 in asphalt, adds eight-foot shoulders and climbing and passing lanes. The improvements will enhance recreational bicycling in this area. This is the first phase of a larger project to improve SH 13 between Rifle and Meeker. |
| Estimated Total Project Cost |
$10,611,868 |
| ARRA Funds |
$10,439,448 |
| Project Status |
Under Construction |
| Start Date |
July 13, 2009 |
| Completion Date |
September 2009 |
| Percentage Spent |
N/A |
| Contractor |
Elam Construction Co. |
-
39.7034888096
-107.936553955
-
- Northwestern (Region 3)
- Project: SH 13 at Rio Blanco Hill
- ARRA
- Projects
-
State Highway 14 between Hatchery and Cameron Pass
-
| Project Owner |
CDOT |
| CDOT Region |
4 |
| County |
Larimer |
| Description of Work |
Resurfaces SH 14 in asphalt. |
| Estimated Total Project Cost |
$5,569,389 |
| ARRA Funds |
$5,478,898 |
| Project Status |
Completed
|
| Start Date |
June 29, 2009 |
| Completion Date |
June 2010 |
| Percentage Spent |
N/A |
| Contractor |
LaFarge West, Inc. |
-
40.690465906
-105.487718582
-
- Project: SH 14 Hatchery to Cameron Pass
- ARRA-CDOT
- Northeastern (Region 4)
- ARRA
- Projects
-
State Highway 257 at Garden Drive in Windsor
-
| Project Owner |
CDOT |
| CDOT Region |
4 |
| County |
Weld |
| Description of Work |
Installs a new traffic signal at this intersection. |
| Estimated Total Project Cost |
$349,676 |
| ARRA Funds |
$344,070 |
| Project Status |
Construction Complete |
| Start Date |
September 15, 2009 |
| Completion Date |
November 2009 |
| Percentage Spent |
100% |
| Contractor |
W.L. Contractors, Inc. |
-
40.472416156
-104.889221191
-
- ARRA
- ARRA-CDOT
- Project: SH 257 and Garden Dr.
- Northeastern (Region 4)
- Projects
-
State Highway 340 in Fruita
-
| Project Owner |
CDOT |
| CDOT Region |
3 |
| County |
Mesa |
| Description of Work |
Installs two new traffic signals west of the I-70 interchange and makes intersection safety improvements for pedestrians and vehicles. |
| Estimated Total Project Cost |
$1,655,141 |
| ARRA Funds |
$1,628,248 |
| Project Status |
Under Contract |
| Start Date |
TBD |
| Completion Date |
TBD |
| Percentage Spent |
N/A |
| Contractor |
Heyl Construction Inc. |
-
39.156088284
-108.736925125
-
- Project: SH 340 in Fruita
- ARRA
- ARRA-CDOT
- Northwestern (Region 3)
- Projects
-
State Highway 52 over Boulder Creek
-
| Project Owner |
CDOT |
| CDOT Region |
4 |
| County |
Boulder |
| Description of Work |
Replaces the SH 52 bridge over Boulder Creek. |
| Estimated Total Project Cost |
$5,060,426 |
| ARRA Funds |
$4,978,205 |
| Project Status |
Completed
|
| Start Date |
August 31, 2009 |
| Completion Date |
August 2010 |
| Percentage Spent |
27% |
| Contractor |
SEMA Construction, Inc. |
-
40.0875279541
-105.057106018
-
- ARRA
- ARRA-CDOT
- Northeastern (Region 4)
- Project: SH 52 over Boulder Creek
- Projects
-
State Highway 60 at I-25 in Johnstown
-
| Project Owner |
CDOT |
| CDOT Region |
4 |
| County |
Weld |
| Description of Work |
Installs a new traffic signal at this intersection. |
| Estimated Total Project Cost |
$501,532 |
| ARRA Funds |
$493,383 |
| Project Status |
Construction Complete |
| Start Date |
August 31, 2009 |
| Completion Date |
November 2009 |
| Percentage Spent |
100% |
| Contractor |
W.L. Contractors, Inc. |
-
40.3352917633
-104.980201721
-
- ARRA
- ARRA-CDOT
- Project: SH 60 and I-25
- Northeastern (Region 4)
- Projects
-
State Highway 62, Dallas Divide between Ridgway and Telluride
-
| Project Owner |
CDOT |
| CDOT Region |
5 |
| County |
San Miguel and Ouray |
| Description of Work |
Bid savings allowed for the project to be increased to resurface a total of 21.5 miles of SH 62 in asphalt and repair embankments. Project includes some work on US 550 as well. |
| Estimated Total Project Cost |
$11,723,191 |
| ARRA Funds |
$4,000,000 |
| Project Status |
Construction Complete |
| Start Date |
May 19, 2009 |
| Completion Date |
October 2009 |
| Percentage Spent |
100% |
| Contractor |
APC Southern Construction Co. |
-
38.0937684096
-107.881965637
-
- ARRA
- ARRA-CDOT
- Project: SH 62 Dallas Divide
- Ouray County
- Southwestern (Region 5)
- San Miguel County
- Projects
-
Overview
-
| Project Owner |
CDOT |
| CDOT Region |
3 |
| County |
Delta |
| Description of Work |
Reconstructs five miles of SH 92 in asphalt and adds passing lanes and shoulders to improve recreational bicycling. |
| Estimated Total Project Cost |
$9,837,484 |
| ARRA Funds |
$9,667,646 |
| Project Status |
Completed
|
| Start Date |
July 13, 2009 |
| Completion Date |
October 2010 |
| Percentage Spent |
N/A |
| Contractor |
Tezak Equipment |
-
38.7969083035
-107.83493042
-
- Project: SH 92 Austin to Hotchkiss
- ARRA
- ARRA-CDOT
- Northwestern (Region 3)
- Projects
-
University (SH 177) between C-470 & Arapahoe Rd
-
| Project Owner |
CDOT |
| CDOT Region |
6 |
| County |
Arapahoe |
| Description of Work |
Resurfaces approximately 1.5 miles of SH 177 in asphalt. |
| Estimated Total Project Cost |
$2,313,025 |
| ARRA Funds |
$1,941,271 |
| Project Status |
Construction Complete |
| Start Date |
June 1, 2009 |
| Completion Date |
August 2009 |
| Percentage Spent |
100.00% |
| Contractor |
LaFarge West, Inc. |
-
39.5779583596
-104.960374832
-
- ARRA
- ARRA-CDOT
- Arapahoe County
- Denver Metro Area (Region 6)
- Project: SH 177 C-470 to Arapahoe Rd.
- Projects
-
US 24/US 285 near Johnson Village
-
| Project Owner |
CDOT |
| CDOT Region |
5 |
| County |
Chaffee |
| Description of Work |
Resurfaces 12.5 miles of US 24/US 285 in asphalt. |
| Estimated Total Project Cost |
$5,168,609 |
| ARRA Funds |
$5,064,720 |
| Project Status |
Construction Complete |
| Start Date |
August 10, 2009 |
| Completion Date |
October 2009 |
| Percentage Spent |
100% |
| Contractor |
Asphalt Paving Co. |
-
38.8282746911
-106.040554047
-
- ARRA
- ARRA-CDOT
- Project: I-76 Sedgwick to Nebraska
- Southwestern (Region 5)
- Chaffee County
- Project: I-70B near Grand Junction
- Projects
- Project: US 24/US 285 Johnson Village
-
US-40 Colfax Ave between Kipling St and Sheridan Blvd
-
| Project Owner |
CDOT |
| CDOT Region |
6 |
| County |
Jefferson |
| Description of Work |
Resurfaces approximately three miles of US 40 in asphalt. |
| Estimated Total Project Cost |
$3,392,313 |
| ARRA Funds |
$3,337,195 |
| Project Status |
Construction Complete |
| Start Date |
June 1, 2009 |
| Completion Date |
September 2009 |
| Percentage Spent |
100% |
| Contractor |
Asphalt Paving Co. |
-
39.740194365
-105.082683563
-
- ARRA
- ARRA-CDOT
- Jefferson County
- Projects
- Project: US 40 Kipling to Sheridan
- Denver Metro Area (Region 6)
-
Overview
-
| Project Owner |
CDOT |
| CDOT Region |
1 |
| County |
Lincoln |
| Description of Work |
This is the next phase of a concrete reconstruction project along this corridor. The project will improve 8.7 miles of US 40/US 287 (mileposts 413-422 approximately). The US 40/US 287 corridor between Campo and Hugo is one of Colorado's 28 high priority strategic projects. |
| Estimated Total Project Cost |
$12,499,486 |
| ARRA Funds |
$12,248,750 |
| Project Status |
Completed
|
| Start Date |
July 14, 2009 |
| Completion Date |
June 2010 |
| Percentage Spent |
100% |
| Contractor |
Castle Rock Construction Co. |
-
38.9775600796
-103.259124756
-
- ARRA
- ARRA-CDOT
- Lincoln County
- Project: US 40/US 287 at Boyero
- Projects
-
US 160 - Alamosa East
-
| Project Owner |
CDOT |
| CDOT Region |
5 |
| County |
Alamosa |
| Description of Work |
Resurfaces six miles of US 160 in asphalt. |
| Estimated Total Project Cost |
$3,758,589 |
| ARRA Funds |
$3,683,041 |
| Project Status |
Construction Complete |
| Start Date |
July 2009 |
| Completion Date |
September 2009 |
| Percentage Spent |
100% |
| Contractor |
Elam Construction Co. |
-
37.4732913779
-105.809240341
-
- Alamosa County
- ARRA
- ARRA-CDOT
- Southwestern (Region 5)
- Project: US 160 Alamosa East
- Projects
-
US 160 at CR 222/223 east of Durango
-
| Project Owner |
CDOT |
| CDOT Region |
5 |
| County |
La Plata |
| Description of Work |
Relocates this intersection and adds auxiliary lanes to improve sight distance. |
| Estimated Total Project Cost |
$8,630,776 |
| ARRA Funds |
$4,000,000 |
| Project Status |
Under Contract |
| Start Date |
TBD |
| Completion Date |
TBD |
| Percentage Spent |
N/A |
| Contractor |
Old Castle SW Group, Inc. dba Four Corners Materials |
-
37.2295083123
-107.764549255
-
- La Plata County
- ARRA
- Southwestern (Region 5)
- Projects
- Project: US 160 at CR 222/223 Durango
-
US 160 east of Durango
-
| Project Owner |
CDOT |
| CDOT Region |
5 |
| County |
La Plata |
| Description of Work |
Constructs a new eastbound on-ramp as part of an already scheduled project that will widen US 160 to four lanes and relocate a traffic signal due to the widening. |
| Estimated Total Project Cost |
$4,000,000 |
| ARRA Funds |
$3,919,600 |
| Project Status |
Completed
|
| Start Date |
September 21, 2009 |
| Completion Date |
September 2010 |
| Percentage Spent |
100% |
| Contractor |
SEMA Construction, Inc. |
-
37.2232207724
-107.856817245
-
- La Plata County
- ARRA
- ARRA-CDOT
- Southwestern (Region 5)
- Project: US 160 East of Durango
- Projects
-
US 160 between Shaw Creek and Del Norte
-
| Project Owner |
CDOT |
| CDOT Region |
5 |
| County |
Rio Grande |
| Description of Work |
Resurfaces three miles of US 160 in asphalt. |
| Estimated Total Project Cost |
$1,683,648 |
| ARRA Funds |
$1,656,292 |
| Project Status |
Construction Complete |
| Start Date |
October 5, 2009 |
| Completion Date |
November 2009 |
| Percentage Spent |
100% |
| Contractor |
Elam Construction Co. |
-
37.6745818046
-106.398639679
-
- ARRA
- ARRA-CDOT
- Project: US 160 Shaw Creek to Del Norte
- Rio Grande County
- Southwestern (Region 5)
- Projects
-
US 285 at Shaffers Crossing
-
| Project Owner |
CDOT |
| CDOT Region |
1 |
| County |
Jefferson |
| Description of Work |
Constructs a grade-separated interchange at Elk Creek Road, new frontage roads and a wildlife crossing underpass. When complete, Elk Creek Rd. will run under US 285. |
| Estimated Total Project Cost |
$10,850,000 |
| ARRA Funds |
$8,400,000 |
| Project Status |
Under Construction |
| Start Date |
September 14, 2009 |
| Completion Date |
September 30, 2011
|
| Percentage Spent |
N/A |
| Contractor |
Hudick Excavating |
-
39.4792680603
-105.369400978
-
- ARRA
- ARRA-CDOT
- Jefferson County
- Project: US 285 at Shaffers Crossing
- Projects
-
US 285 south of Saguache
-
| Project Owner |
CDOT |
| CDOT Region |
5 |
| County |
Saguache |
| Description of Work |
Resurfaces eight miles of US 285 in asphalt. |
| Estimated Total Project Cost |
$4,877,871 |
| ARRA Funds |
$4,779,826 |
| Project Status |
Construction Complete |
| Start Date |
August 27, 2009 |
| Completion Date |
November 2009 |
| Percentage Spent |
100% |
| Contractor |
Elam Construction Co. |
-
38.0352476267
-106.142091751
-
- Project: US 285 South of Saguache
- ARRA
- ARRA-CDOT
- Saguache County
- Southwestern (Region 5)
- Projects
-
Overview
-
| Project Owner |
CDOT |
| CDOT Region |
2 |
| County |
Baca |
| Description of Work |
This project will reconstruct US 287 in concrete and improve drainage and shoulder embankments. The US 40/US 287 corridor between Campo and Hugo is one of Colorado's 28 high priority strategic projects. |
| Estimated Total Project Cost |
$16,000,000 |
| ARRA Funds |
$15,677,776 |
| Project Status |
Completed
|
| Start Date |
October 26, 2009 |
| Completion Date |
September 2010 |
| Percentage Spent |
N/A |
| Contractor |
Lawson Construction Co. |
-
37.3283996446
-102.615737915
-
- ARRA
- ARRA-CDOT
- Baca County
- Project: US 287 South of Springfield
- Projects
-
US 34 at Weld County Road 49
-
| Project Owner |
CDOT |
| CDOT Region |
4 |
| County |
Weld |
| Description of Work |
Installs a new traffic signal at this intersection. |
| Estimated Total Project Cost |
$469,861 |
| ARRA Funds |
$462,227 |
| Project Status |
Completed |
| Start Date |
October 26, 2009 |
| Completion Date |
April 2010 |
| Percentage Spent |
N/A |
| Contractor |
DKS Enterprises |
-
40.3919270109
-104.593019485
-
- ARRA
- ARRA-CDOT
- Project: US 34 at Weld County Road 49
- Northeastern (Region 4)
- Projects
-
US 36 at Broadway in Boulder
-
| Project Owner |
CDOT |
| CDOT Region |
4 |
| County |
Boulder |
| Description of Work |
Installs a new traffic signal at this intersection. |
| Estimated Total Project Cost |
$393,304 |
| ARRA Funds |
$386,913 |
| Project Status |
Construction Complete |
| Start Date |
August 3, 2009 |
| Completion Date |
Janaury 2010 |
| Percentage Spent |
100% |
| Contractor |
DKS Enterprises |
-
40.0655263691
-105.28181076
-
- ARRA
- ARRA-CDOT
- Project: US 36 at Broadway
- Northeastern (Region 4)
- Projects
-
US 36 between Estes Park and Lyons
-
| Project Owner |
CDOT |
| CDOT Region |
4 |
| County |
Boulder and Larimer |
| Description of Work |
Chip seals 22 miles of US 36 to improve the roadway surface condition. |
| Estimated Total Project Cost |
$1,679,863 |
| ARRA Funds |
$1,652,568 |
| Project Status |
Construction Complete |
| Start Date |
August 3, 2009 |
| Completion Date |
September 2009 |
| Percentage Spent |
100% |
| Contractor |
United Companies |
-
40.3016543474
-105.383906364
-
- Project: US 36 Estes Park to Lyons
- ARRA
- ARRA-CDOT
- Northeastern (Region 4)
- Projects
-
US 6, State Highway 93, State Highway 58 (one intersection in Golden) and State Highway 128 at Simms Street
-
| Project Owner |
CDOT |
| CDOT Region |
6 |
| County |
Jefferson and Broomfield |
| Description of Work |
Replaces traffic signals at two locations |
| Estimated Total Project Cost |
$901,629 |
| ARRA Funds |
$886,979 |
| Project Status |
Construction Complete |
| Start Date |
July 7, 2009 |
| Completion Date |
March 2010 |
| Percentage Spent |
94% |
| Contractor |
Sturgeon Electric Co. |
-
39.7545807793
-105.236363411
-
- Broomfield County
- ARRA
- Jefferson County
- Denver Metro Area (Region 6)
- Projects
- Project: US 6/SH 93/SH 58
|