I-25 between 6th Avenue and 23rd Avenue

Red Marker I-25 between 6th Avenue and 23rd Avenue
Project Owner CDOT
CDOT Region 6
County Denver
Description of Work Resurfaces approximately three miles of I-25 in asphalt.
Estimated Total Project Cost $4,259,920
ARRA Funds $4,190,706
Project Status Under Construction- In winter shutdown
Start Date June 14, 2009
Completion Date April 2010
Percentage Spent 76%
Contractor Brannan Sand and Gravel Co.

 

 

39.7389898615 -105.01404047
  • Project: I-25 6th to 23rd
  • ARRA-CDOT
  • Denver County
  • Denver Metro Area (Region 6)
  • ARRA
  • Projects
Project Owner CDOT
CDOT Region 6
County Denver
Description of Work Resurfaces approximately three miles of I-25 in asphalt.
Estimated Total Project Cost $4,259,920
ARRA Funds $4,190,706
Project Status Under Construction- In winter shutdown
Start Date June 14, 2009
Completion Date April 2010
Percentage Spent 76%
Contractor Brannan Sand and Gravel Co.