- Info
Construction Updates
CDOT is always working to keep the C-470 Corridor safe. Ongoing maintenance and construction make that possible. We've listed the current projects below.
Project Description: Placement of wire rope safety fence in the median
The Wire Rope Safety fence project from Broadway to Quebec is finished. It was constructed and closed last fall/winter. It was a night job with left lane closures in both directions. There is another Median cable rail project from Broadway to Wadsworth (Project #15552) in the early stages, with an Ad date of 6/29/06. This project will be a night job as well, with left lane closures in both directions during construction.
PROJECT COMPLETED
Project Description: Ramp Improvements to C-470/I-70 Interchange
Project Limits: C-470 /I-70 Interchange
Time Frame: March 2005
Traffic Impact:The following ramps will be built
C Ramp which is the existing NB C-470 to EB I-70 will be relocated
E Ramp is a new ramp for SB C-470 to WB I-70
F Ramp is also a new ramp for EB I-70 to NB C-470
PROJECT COMPLETED
Project Description: Ramp Metering
Project Limits: SB Santa Fe to WB C-470
Time Frame: Summer 2004
Traffic Impact: Minimal Existing EB I-70 to SB C-470 will be widened
PROJECT COMPLETED
Project Description: Resurfacing (night job)
Project Limits: C-470 Ken Caryl to Wadsworth
Time Frame: Early September for project completion
Traffic Impact: One lane closure at a time
PROJECT COMPLETED
Project Description: Ramp metering
Project Limits: Westbound at Quincy, Bowles, University and Broadway
Time Frame: Summer 2003
Traffic Impact: Minimal
PROJECT COMPLETED