American Recovery & Reinvestment Act (ARRA)
|
| ARRA Project Status (December 31, 2009)* | Highway | Transit | Total |
| Gone to Advertisement | 83 | 38 | 121 |
| Under Contract | 71 | 27 | 98 |
| Under Construction or Near Construction | 65 | 25 | 90 |
|
Construction Complete |
17 | 5 | 22 |
*The project status will be updated once a month.
To track national and local progress of the ARRA visit:
Federal Highway Adminstration Recovery Web site
Colorado Economic Recovery and Accountability Web site
Jobs Data (as of May 31)
65 jobs created or sustained
2,224 payroll hours
$12,537 in payroll expenses
Jobs Data (as of June 30)
576 jobs created or sustained
26,706 payroll hours
$661,621 in payroll expenses
Job Data (as of July 31)
1,685 jobs created or sustained
86,332 payroll hours
$2.14 million in payroll expenses
Jobs Data (as of August 31)
3512 Direct Jobs Created or Sustained (+1,827 from the July 31st report)
195,378 Direct Job Hours Created or Sustained (+109,046 from the July 31st report)
$4.795 M Payroll from Job Hours Created or Sustained (+2.655 M from the July 31st report)
Jobs Data (as of September 30)
6,018 Direct Jobs Created or Sustained (+2,506 from the August 31st report)
344,852 Direct Job Hours Created or Sustained (+149,474 from the August 31st report)
$8.605 M Payroll from Job Hours Created or Sustained (+3.81 M from the August 31st report)
Jobs Data- Highway (as of October 31)
9,815 Direct Jobs Created or Sustained (+3,797 from the September 30th report)
506,836 Direct Job Hours Created or Sustained (+161,984 from the September 30th report)
$12.6 M Payroll from Job Hours Created or Sustained (+4 M from the September 30th report)
Jobs Data- Transit (as of October 31)- First month of transit data
467 Direct Jobs Created or Sustained
212,288 Direct Job Hours Created or Sustained
$439,567 Payroll from Job Hours Created or Sustained
Jobs Data- Highway and Transit (as of October 31)- First month of highway + tranist data
10,282 Direct Jobs Created or Sustained
719,124 Direct Job Hours Created or Sustained
$13 M Payroll from Job Hours Created or Sustained
ARRA Transportation Spending - Highway (Colorado - as of November 30, 2009)
75 Projects Put out to Bid worth $333,794,005
69 Projects Under Contract worth $263,319,325
64 Projects Under Construction or Starting Soon worth $260,850,407
14 Projects Construction Complete worth $31,682,870
ARRA Job Information - Highway (Colorado - as of November 30, 2009)
12,482 Direct Jobs Created or Sustained
647,014 Direct Job Hours Created or Sustained
$16,746,905 Payroll from Job Hours Created or Sustained
ARRA Transportation Spending - Transit (Colorado - as of November 30, 2009)
35 Projects Put out to Bid worth $94,583,948
27 Projects Under Contract worth $79,546,530
24 Projects Under Construction or Starting Soon worth $73,544,530
4 Projects Complete $175,442
ARRA Job Information - Transit (Colorado - as of November 30, 2009)
512 Direct Jobs Created or Sustained
220,958 Direct Job Hours Created or Sustained
$550,461 Payroll from Job Hours Created or Sustained
ARRA Transportation Spending - Highway and Transit (Colorado - as of November 30, 2009)
110 Projects Put out to Bid worth $428,377,953
96 Projects Under Contract worth $342,865,855
88 Projects Under Construction or Starting Soon worth $334,394,937
18 Projects Complete worth $31,858,312
ARRA Job Information - Highway and Transit (Colorado - as of November 30, 2009)
12,994 Direct Jobs Created or Sustained
867,972 Direct Job Hours Created or Sustained
$17,297,366 Payroll from Job Hours Created or Sustained
ARRA Transportation Spending - Highway (Colorado - as of December 31, 2009)
83 Projects Put out to Bid worth $355,013,948
71 Projects Under Contract worth $303,918,006
65 Projects Under Construction or Starting Soon worth $266,784,359
17 Projects Construction Complete worth $38,796,482
ARRA Job Information - Highway (Colorado - as of December 31, 2009)
14,421 Direct Jobs Created or Sustained
742,312 Direct Job Hours Created or Sustained
$18,913,676 Payroll from Job Hours Created or Sustained
ARRA Transportation Spending - Transit (Colorado - as of December 31, 2009)
38 Projects Put out to Bid worth $93,133,948
27 Projects Under Contract worth $71,955,739
25 Projects Under Construction or Starting Soon worth $62,202,210
5 Projects Complete $244,086
ARRA Job Information - Transit (Colorado - as of December 31, 2009)
551 Direct Jobs Created or Sustained
238,113 Direct Job Hours Created or Sustained
$1,004,987 Payroll from Job Hours Created or Sustained
ARRA Transportation Spending - Highway and Transit (Colorado - as of December 31, 2009)
121 Projects Put out to Bid worth $448,147,896
98 Projects Under Contract worth $375,973,745
90 Projects Under Construction or Starting Soon worth $328,986,569
22 Projects Complete worth $39,040,568
ARRA Job Information - Highway and Transit (Colorado - as of December 31, 2009)
14,972 Direct Jobs Created or Sustained
980,425 Direct Job Hours Created or Sustained
$19,918,663 Payroll from Job Hours Created or Sustained
Concrete Repairs Continue on Eastbound C-470 This Weekend
Feb 05, 2010
Weekend Work on C-470 Resumes for Concrete Repairs
Jan 29, 2010
Colorado Ranks 4th in Nation in Recovery Act Transparency
Jan 26, 2010
Traffic Signals Now Operational at US 34 and Weld County Road 49
Jan 25, 2010
SH 92 American Recovery & Reinvestment Act Project Suspended Through Winter Months
Jan 14, 2010